The Strength & Power of Our Company
We have a lot of experienced education staff from CMAA who are ngaged in IT certification examination more than 8 years. They are familiar with past Construction-Manager real exam questions and they know update information about the Construction-Manager exam at first time. Our Construction-Manager Prep & test bundle or exam cram pdf are shown on the website with the latest version. Our IT staff will check the update every day.
Are you still worried about CMAA Construction-Manager? I advise you to google "Prep4cram". We provide you Construction-Manager free demo download for your reference. Construction-Manager Prep & test bundle is very useful and similar with the real exams. If you are willing to pass exam at first shot you had better purchase exam cram, we will send you the exam cram PDF file. It is very available for reading at all electronics and printing out. The most important is that we guarantee: "No Pass, No Pay". We already help more than 3000 candidates pass this exam. We are proud to say that about passing Construction-Manager we are the best.
Up-to-date Version, Latest, Valid
We promise Construction-Manager exam cram all we sold is the latest and valid version. If you have doubt about it, you can contact with us. Also you can compare our version with the other. Normally if it is not the latest version we won't say 100% pass rate, we will say 70%-80% pass rate and advise you waiting the updated version. We hereby specially certify that the Construction-Manager exam cram we say 100% pass is the latest and valid version. Do not hesitate about it, just buy it
Our Golden Service
Firstly we are 7*24 on-line services, once you contact with us we will reply you in two hours;
Secondly we have one-year warranty service since you buy. We will send you the updated Construction-Manager exam version within one year if you accept. No matter you have any question you can email us to solve it.
Thirdly we will keep your information safe. Even our service customers can't see your complete information. We have a strict information protection system.
Fourthly we guarantee Construction-Manager exam 100% pass rate if you study our Construction-Manager prep material hard. But if you fail the exam please provide the unqualified certification scanned and email to us. Once we confirm it we will full refund to you.
Fifthly if you buy Construction-Manager exam cram for your company and want to get the latest version in next several years we are free to serve you in one year and you can give 50% discount Construction-Manager Prep & test bundle in next year. Also after you buy you will have priority to get our holiday discount or sale coupon. If you pass Construction-Manager exam and want to buy other subject we can give you discount too.
All in all we have confidence about Construction-Manager exam that we are the best. If you want to pass it successfully please choose our Construction-Manager exam cram pdf. You will be happy about your choice. It's certainly worth it.
CMAA Certified Construction Manager (CCM) Sample Questions:
1. At what stage of the design phase shall the CM conduct a constructability review?
A) 90% design stage
B) Throughout the design process including 100% design documents
C) 60% design stage
D) 30% design stage
2. What are the essential components of the Risk Management process?
A) Avoiding, mitigating, transferring, accepting
B) Communicating and reporting, tracking, mitigation, resolution
C) Avoiding, tracking, mitigation, transferring
D) Communicating and reporting, assessing, mitigation, tracking
3. As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
A) Scope reduction will reduce overall project budget.
B) Interface with the design-build team is not needed at this time.
C) Life cycle and maintenance costs should not be considered.
D) A multi-discipline review on functions and alternate solutions.
4. When applying BIM to a project, which method checks for interferences by searching for intersecting volumes?
A) Clash Detection
B) Parametric Modeling
C) BIM Integration
D) Virtual Design and Construction (VDC)
5. An owner requests a cost estimate for a project during the design phase with an estimated present-day budget of $10M. Construction is scheduled for 24 months. Escalation is 5% for the project duration. What is the projected cost for the project?
A) $10,500,000
B) $5,375,000
C) $11,000,000
D) $5,187,500
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: A | Question # 3 Answer: D | Question # 4 Answer: A | Question # 5 Answer: C |