Microsoft 70-178 : Microsoft Project 2010, Managing Projects

70-178 real exams

Exam Code: 70-178

Exam Name: Microsoft Project 2010, Managing Projects

Updated: Oct 02, 2026

Q & A: 70 Questions and Answers

Already choose to buy "PDF"
Price: $59.99 

About Microsoft 70-178 Exam

Our Golden Service

Firstly we are 7*24 on-line services, once you contact with us we will reply you in two hours;

Secondly we have one-year warranty service since you buy. We will send you the updated 70-178 exam version within one year if you accept. No matter you have any question you can email us to solve it.

Thirdly we will keep your information safe. Even our service customers can't see your complete information. We have a strict information protection system.

Fourthly we guarantee 70-178 exam 100% pass rate if you study our 70-178 prep material hard. But if you fail the exam please provide the unqualified certification scanned and email to us. Once we confirm it we will full refund to you.

Fifthly if you buy 70-178 exam cram for your company and want to get the latest version in next several years we are free to serve you in one year and you can give 50% discount 70-178 Prep & test bundle in next year. Also after you buy you will have priority to get our holiday discount or sale coupon. If you pass 70-178 exam and want to buy other subject we can give you discount too.

All in all we have confidence about 70-178 exam that we are the best. If you want to pass it successfully please choose our 70-178 exam cram pdf. You will be happy about your choice. It's certainly worth it.

Up-to-date Version, Latest, Valid

We promise 70-178 exam cram all we sold is the latest and valid version. If you have doubt about it, you can contact with us. Also you can compare our version with the other. Normally if it is not the latest version we won't say 100% pass rate, we will say 70%-80% pass rate and advise you waiting the updated version. We hereby specially certify that the 70-178 exam cram we say 100% pass is the latest and valid version. Do not hesitate about it, just buy it

The Strength & Power of Our Company

We have a lot of experienced education staff from Microsoft who are ngaged in IT certification examination more than 8 years. They are familiar with past 70-178 real exam questions and they know update information about the 70-178 exam at first time. Our 70-178 Prep & test bundle or exam cram pdf are shown on the website with the latest version. Our IT staff will check the update every day.

Free Download real 70-178 prep cram

Are you still worried about Microsoft 70-178? I advise you to google "Prep4cram". We provide you 70-178 free demo download for your reference. 70-178 Prep & test bundle is very useful and similar with the real exams. If you are willing to pass exam at first shot you had better purchase exam cram, we will send you the exam cram PDF file. It is very available for reading at all electronics and printing out. The most important is that we guarantee: "No Pass, No Pay". We already help more than 3000 candidates pass this exam. We are proud to say that about passing 70-178 we are the best.

Microsoft 70-178 Exam Syllabus Topics:

SectionObjectives
Reporting and Communication- Communicate project status to stakeholders
- Generate project reports and dashboards
Customizing Microsoft Project- Customize views, tables, and fields
- Configure project settings and templates
Managing and Tracking Projects- Handle project changes and baselines
- Manage resource allocation and workload
- Track project progress and update schedules
Initiating Projects- Define project scope and objectives
- Identify stakeholders and project constraints
Planning Projects- Create and configure project plans in Microsoft Project 2010
- Define tasks, dependencies, and milestones
- Assign resources and optimize schedules

Microsoft Project 2010, Managing Projects Sample Questions:

Question #1

You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?

  • A. Use a work type resource.
  • B. Create a custom field and capture travel costs at the project level.
  • C. Use a budget resource.
  • D. Use a cost type resource.
Reveal Solution  Discussion  0

Correct Answer: A  🗳️

Question #2

You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?

  • A. View the deadline date for the task
  • B. Click Calculate project
  • C. Use the Task Inspector tool and view the start and finish dates
  • D. Use the Task Inspector tool and view the resource calendar
Reveal Solution  Discussion  0

Correct Answer: D  🗳️

Question #3

DRAG DROP You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. (Click the Exhibit button.) Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam's workload? (To answer, drag the appropriate units to the correct locations in the answer area.)

  • A. 75%, 100%
  • B. 100%, 150%
  • C. 75%, 75%
  • D. 100%, 100%
Reveal Solution  Discussion  0

Correct Answer: C  🗳️

Question #4

You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?

  • A. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
  • B. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Entire project radio button, and then click OK.
  • C. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
  • D. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, and then click OK.
Reveal Solution  Discussion  0

Correct Answer: C  🗳️

Question #5

You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?

  • A. Click the Insert Milestone button.
  • B. Select the Mark Task as Milestone check box.
  • C. Remove the predecessor assignments.
  • D. Change Work to zero hours.
Reveal Solution  Discussion  0

Correct Answer: B  🗳️

What Clients Say About Us

I found your 70-178 material to be a good value. I passed the 70-178 with it. Prep4cram exam material is the most important material which you need to have prepared for your exam.

Devin Devin       4.5 star  

Clear the 70-178 exam this Tuesday. Thank you!

Afra Afra       4.5 star  

Thank you so much for your great 70-178 product and service.

Tyrone Tyrone       4 star  

How many of you can assure me that the material you have used for your exam preparation would provide you guaranteed success. I am sure that none of you can give me this guarantee. But Prep4cram gives you that. Prep4cram assures you 100% success by providing you the best quality notes for your preparation. I have sought guidance from Prep4cram for my 70-178 exams and have got pleasing results.

Regina Regina       5 star  

Good luck to all!
Your site is so helpful for all candidates who want to get latest and high quality exams, just passed the latest updated 70-178 exam by using your exam dumps

Giselle Giselle       4 star  

I will recommend Prep4cram to my friends.

Adolph Adolph       4 star  

I didn’t expect honestly that i will succeed because i failed last time with the other exam materials, but this 70-178 practice engine worked. I did pass this time! Cool!

Nydia Nydia       4 star  

Trust me, my friend. This 70-178 material is realiable. Do not hesitate to buy it.

Una Una       4.5 star  

Well, I can't say that everything went smoothly on the 70-178 exam, but your 70-178 braindumps helped me to be more confident, I passed 70-178 exam yesterday!

Camille Camille       5 star  

Passed my 70-178 exam today, I am so happy. Thanks, Prep4cram for these excellent 70-178 dumps.

Cleveland Cleveland       4 star  

Dumps are the latest as they say. It is nearly same with real examination. Passed 70-178 without doubt.

Hedda Hedda       4 star  

Thanks for your 70-178 study guide, I have passed it.

Elroy Elroy       5 star  

Passed 70-178 exam this morning. 70-178 dumps are valid on 90%. Got just 2 new ones.

Nelson Nelson       5 star  

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Why Choose Prep4cram

Quality and Value

Prep4cram Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Prep4cram testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Prep4cram offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.

Our Clients

amazon
centurylink
charter
comcast
bofa
timewarner
verizon
vodafone
xfinity
earthlink
marriot
vodafone