Our Golden Service
Firstly we are 7*24 on-line services, once you contact with us we will reply you in two hours;
Secondly we have one-year warranty service since you buy. We will send you the updated 70-178 exam version within one year if you accept. No matter you have any question you can email us to solve it.
Thirdly we will keep your information safe. Even our service customers can't see your complete information. We have a strict information protection system.
Fourthly we guarantee 70-178 exam 100% pass rate if you study our 70-178 prep material hard. But if you fail the exam please provide the unqualified certification scanned and email to us. Once we confirm it we will full refund to you.
Fifthly if you buy 70-178 exam cram for your company and want to get the latest version in next several years we are free to serve you in one year and you can give 50% discount 70-178 Prep & test bundle in next year. Also after you buy you will have priority to get our holiday discount or sale coupon. If you pass 70-178 exam and want to buy other subject we can give you discount too.
All in all we have confidence about 70-178 exam that we are the best. If you want to pass it successfully please choose our 70-178 exam cram pdf. You will be happy about your choice. It's certainly worth it.
Up-to-date Version, Latest, Valid
We promise 70-178 exam cram all we sold is the latest and valid version. If you have doubt about it, you can contact with us. Also you can compare our version with the other. Normally if it is not the latest version we won't say 100% pass rate, we will say 70%-80% pass rate and advise you waiting the updated version. We hereby specially certify that the 70-178 exam cram we say 100% pass is the latest and valid version. Do not hesitate about it, just buy it
The Strength & Power of Our Company
We have a lot of experienced education staff from Microsoft who are ngaged in IT certification examination more than 8 years. They are familiar with past 70-178 real exam questions and they know update information about the 70-178 exam at first time. Our 70-178 Prep & test bundle or exam cram pdf are shown on the website with the latest version. Our IT staff will check the update every day.
Are you still worried about Microsoft 70-178? I advise you to google "Prep4cram". We provide you 70-178 free demo download for your reference. 70-178 Prep & test bundle is very useful and similar with the real exams. If you are willing to pass exam at first shot you had better purchase exam cram, we will send you the exam cram PDF file. It is very available for reading at all electronics and printing out. The most important is that we guarantee: "No Pass, No Pay". We already help more than 3000 candidates pass this exam. We are proud to say that about passing 70-178 we are the best.
Microsoft 70-178 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Reporting and Communication | - Communicate project status to stakeholders - Generate project reports and dashboards |
| Customizing Microsoft Project | - Customize views, tables, and fields - Configure project settings and templates |
| Managing and Tracking Projects | - Handle project changes and baselines - Manage resource allocation and workload - Track project progress and update schedules |
| Initiating Projects | - Define project scope and objectives - Identify stakeholders and project constraints |
| Planning Projects | - Create and configure project plans in Microsoft Project 2010 - Define tasks, dependencies, and milestones - Assign resources and optimize schedules |
Microsoft Project 2010, Managing Projects Sample Questions:
1. You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?
A) Use a work type resource.
B) Create a custom field and capture travel costs at the project level.
C) Use a budget resource.
D) Use a cost type resource.
2. You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?
A) View the deadline date for the task
B) Click Calculate project
C) Use the Task Inspector tool and view the start and finish dates
D) Use the Task Inspector tool and view the resource calendar
3. DRAG DROP You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. (Click the Exhibit button.) Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam's workload? (To answer, drag the appropriate units to the correct locations in the answer area.)
A) 75%, 100%
B) 100%, 150%
C) 75%, 75%
D) 100%, 100%
4. You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?
A) ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
B) ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Entire project radio button, and then click OK.
C) ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
D) ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, and then click OK.
5. You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
A) Click the Insert Milestone button.
B) Select the Mark Task as Milestone check box.
C) Remove the predecessor assignments.
D) Change Work to zero hours.